Transmission ‘lines cut’ affected bulk power supply to Lagos – TCN

This is contained in a statement issued by Mrs Ndidi Mbah, TCN’S General Manager, Public Affairs in a statement in Abuja on Tuesday.
According to Mbah, the incident occurred on Sunday.
She said that the incident resulted in a reduction of approximately 350 Megawatts (MW) of bulk electricity supply to Lagos affecting both Eko and Ikeja Electricity Distribution Companies.
According to her, the temporary drop in bulk power supply caused a significant load shedding within the Eko and Ikeja franchise areas.
She said TCN had mobilised its engineers to the site and conveyed necessary materials to repair the snapped sections of the 330kV Omotoso – Ikeja West transmission line.
”Repair work is expected to be completed within three days, after which the full bulk power supply will be restored through the transmission line route.
”TCN apologises for any inconvenience caused to the government, Eko and Ikeja Electricity Distribution companies, and electricity consumers in Lagos,”she said.